Waves Fluid Engineering removes old, leaking or corroded water tanks and installs new FRP / GRP, pressed steel and stainless steel panel tanks in their place. We plan the changeover around your building’s water supply, build the new tank to current PUB requirements and hand it over tested.
Not sure whether to repair or replace? Send photos of the tank on WhatsApp and we will advise.
A water tank needs replacing when it can no longer hold water reliably or keep it clean, and a repair would only buy a little time. In practice that means leaks at several joints, corroded supports, deformed panels or rust-through, usually on a tank that is around twenty years old.
A tank with one local defect is a different case. A single cracked or leaking panel can usually be replaced on its own, without rebuilding the tank. The table below sets out what we look for and what we normally recommend.
| What you see | What it usually means | Usual answer |
|---|---|---|
| Leaks at several joints, or leaks that come back after repair | The sealant and joints have aged across the whole tank, not in one spot. | Replace the tank |
| One cracked or leaking panel | Local damage. The rest of the tank is sound. | Repair: replace the panel |
| Corroded stays, tie rods, bolts or brackets | The parts that hold the panels against the weight of the water are weakening. | Replace if widespread, repair if limited |
| Bulging, bowed or deformed panels | The structure is no longer carrying the load evenly. | Replace the tank |
| Rust-through or a failed coating on a pressed steel tank | The steel itself is thinning. | Replace the tank |
| Roof panels that are cracked, sagging or no longer sealing | Dirt, insects and rainwater can get into the stored water. | Replace the roof, or the tank if the walls have aged too |
| A tank around twenty years old with repair bills rising | The tank is near the end of its service life. | Plan a replacement |
| The capacity or layout no longer suits the building | For example, a single-compartment tank that cannot be cleaned without shutting off the supply. | Replace with the right size and compartments |
We do both, so the recommendation follows the condition of the tank. If the tank is near the end of its service life, we advise replacement over repeated repairs. If it is sound apart from one defect, we repair it.
Suits a sound tank with a local defect.
Lower cost and little disruption. Worth doing when the rest of the tank has years left in it. See tank repair and maintenance.
Suits an ageing tank with defects in several places.
Two-year warranty on newly installed FRP / GRP tanks, subject to terms and conditions.
A replacement is more than a new set of panels. This is what happens to each part of the tank. The numbers match the diagram at the top of this page.
Drained, dismantled panel by panel, carried out of the plant room or off the roof, and disposed of.
All new, and certified to the standard for the tank’s use. Panels come in four sizes, so the new tank can match the old footprint or be resized.
New lockable manhole covers and air vents, normally one vent for each compartment unless your consultant specifies more.
All new. The panels are assembled, bolted and sealed on site.
Inspected at the site visit and reused if they are level, sound and match the new tank. Standard plinth spacing is 1 m centre to centre. A 2 m spacing needs an I-beam skid base.
The pipework is reconnected to the new tank, and internal and external ladders and level controls are fitted. Tanks 3 m or higher get a guard rail on the roof and a safety cage on the external ladder. Worn valves, including the ball float valve, can be changed at the same time.
The new tank is filled, leak tested and commissioned, then handed over with its warranty and the documents for your building records.
The use of the tank decides the material. Drinking water tanks are normally replaced with FRP / GRP or SS316 stainless steel. Sprinkler, fire and hosereel tanks are replaced with pressed steel.
| New tank | Used for | Standard | Good to know |
|---|---|---|---|
| FRP / GRP panel tank | Potable water, NEWater, cooling tower and rainwater. | SS 245:2014 | The most common potable water tank in Singapore. Available with insulated panels. FRP, GRP and SMC are names for the same tank. |
| SS316 stainless steel tank | Drinking water and food processing. | Grade 316, BS EN 10088-2:2014 | Chosen where a higher specification than FRP / GRP is wanted. Higher corrosion resistance than grade 304. |
| HDG pressed steel tank | Sprinkler, fire and hosereel water. | SS 22:1979 and SCDF requirements | Hot-dip galvanised, so it suits outdoor locations. |
| Bitumen painted pressed steel tank | Indoor sprinkler, fire and hosereel tanks. | SS 22:1979 and SCDF requirements | Black bituminous coating, for indoor plant rooms. |
| SS304 stainless steel tank | Non-potable duties: hosereel, sprinkler, fire, chemical and treated water. | Grade 304 | Strong corrosion resistance. Not used for drinking water. |
Like-for-like is not always possible, or wise. PUB’s current standards for potable water tanks are SS 245:2014 for FRP / GRP and grade 316 stainless steel, so an older tank of a different specification is replaced with one that meets them. Replacement is also the time to add a second compartment or correct the capacity.
This is the first question most building managers ask. There are three ways to do it, and the right one depends on the tank and the building. We agree the method with you at the site visit, before any work starts.
If the tank has two compartments, one keeps supplying the building while the other is dismantled and rebuilt. Then they swap.
Suits dual-compartment tanks.
For a tank with a single compartment, a temporary tank or a bypass line carries the building while the new tank goes in.
Suits buildings that cannot accept a shutdown.
For smaller tanks, and buildings that can accept it, the changeover is done during a short shutdown at a time agreed in advance.
Suits small tanks and off-peak hours.
Sprinkler and hosereel tanks supply the fire-fighting system, so their shutdown is agreed with your fire safety manager before work starts.
From the first call to a tested tank, the work follows six steps.
Both depend on the tank and the site, which is why we quote after a site visit and not from a price list.
A simple panel tank is typically installed in a few days. A replacement adds the time needed to drain, dismantle and remove the old tank, and to keep the supply running while that happens.
The programme depends on three things: the size of the tank, access to the plant room or roof, and how much work the old tank takes to remove.
There is no fixed price. Ask for a free written quotation.
A replacement tank has to meet the rules in force today, not the ones that applied when the old tank was installed. These are the ones that matter most.
PUB classes the replacement of tanks in the drinking water supply system as water service plumbing work. Since 1 April 2018 it has been an offence to engage a plumber who is not licensed by PUB for regulated water service work. See PUB’s page on plumbing works.
Must comply with SS 245:2014. Tanks tested to the older 1995 edition of the standard have not been accepted since 1 June 2019.
Must be grade 316 or better, tested to BS EN 10088-2:2014, and stainless steel throughout, including the bottom panels and the roof cover.
PUB’s standards for sectional tanks place the structural soundness of the tank, and the compliance of the installation, with a Professional Engineer.
Sprinkler, fire and hosereel tanks are built to SS 22 and SCDF requirements.
The annual rule still applies. A licensed plumber must inspect the tank, clean and disinfect it where necessary, and certify it at least once every 12 months. See PUB’s water storage tank requirements and our tank washing service.
We handle the PUB submission as part of the job where it is required.
Newly installed FRP / GRP tanks carry a two-year warranty from the date of installation, subject to terms and conditions. The tanks and spare parts we use come from globally recognised manufacturers.
We replace tanks in occupied, working buildings across Singapore, whoever installed the original tank:
Replace the tank when the problem is spread across it rather than in one place: leaks at several joints, leaks that return after repair, corroded stays and bolts, bulging or deformed panels, or rust-through on a steel tank. A single cracked or leaking panel can usually be replaced on its own. If the tank is close to the end of its service life, we advise replacement over repeated repairs.
We treat a sectional water tank as roughly a twenty-year asset. The actual life depends on the tank material, whether it sits indoors or on an exposed roof, the water it holds, and how regularly it is cleaned and inspected.
Not for the whole job in most buildings. Where the tank has two compartments, one stays in service while the other is replaced. Where it has one, supply can be kept up with a temporary tank or a bypass, or the changeover is scheduled as a short planned shutdown. We agree the method with you at the site visit, before any work starts.
It depends on the size of the tank, access to the plant room or roof, and how much work the old tank takes to dismantle and remove. A simple panel tank is typically installed in a few days. After the site visit we can tell you how long your job should take.
There is no fixed price. The cost depends on the tank capacity and material, access for removing the old panels and bringing in the new ones, the condition of the base, any pipework changes, and how the water supply is kept running during the work. We provide a free written quotation after a site visit.
For drinking water, yes. FRP / GRP panel tanks certified to SS 245:2014 are the most common choice for potable water in Singapore, and SS316 stainless steel is used where a higher specification is wanted. Sprinkler, fire and hosereel tanks are normally replaced with pressed steel tanks built to SS 22 and SCDF requirements.
Yes, as long as the base, the plant room and the pipework allow it. Replacement is the best time to correct the capacity or to split the tank into two compartments, so that one cell can be isolated for cleaning or repair while the other stays in service. Potable water tanks are limited to 4 m in height.
Often, yes. We inspect the plinths and skid base during the site visit and reuse them if they are level, sound and match the new tank. Standard plinth spacing is 1 m centre to centre, and a 2 m spacing needs an I-beam skid base. Existing pipework is reconnected, and worn valves can be changed at the same time.
Yes. The old tank is drained, dismantled panel by panel, carried out and disposed of as part of the replacement.
PUB treats the replacement of a tank in a drinking water system as regulated water service work, which must be carried out by a PUB licensed plumber. New potable water tanks must also meet PUB's stipulated standards. We handle the PUB submission as part of the job where it is required.
Yes. Individual replacement panels are available, and a single cracked or leaking panel can usually be changed without rebuilding the tank. If the site check shows that the rest of the tank is sound, we recommend the smaller job.
Yes. We repair, service and replace water tanks regardless of who installed them.
Newly installed FRP / GRP tanks carry a two-year warranty from the date of installation, subject to terms and conditions.
Yes. PUB requires the party responsible for a water storage tank to engage a licensed plumber at least once every 12 months to inspect it, clean and disinfect it where necessary, and certify it. A new tank follows the same rule.
Send us the size of the tank, what it is used for and a few photos, or ask for a site visit. We will tell you whether it needs a repair or a new tank, and quote for it.